Across 609 qualifying US industrial recommendations, the median projected simple payback was 1.581 years. The middle half ran from 0.8344 to 2.708 years. Those figures describe the assessed proposals for waste compaction before collection, in fiscal years 1988 to 2026.

The scope of the plant change

Start with the actual collection contract. Reducing skip volume helps when haulage or lift count drives the bill. Weigh the waste and record container fill before and after a trial, including the electricity and labour used by the compactor.

A recommendation you can reproduce

Recommendation SD036509 in US fiscal year 2005 pairs US$18,500 of implementation cost with US$11,700 in estimated annual net savings. Dividing the first figure by the second gives 1.581 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$9,788 and the median annual saving was US$6,421. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for waste compaction before collection. Lower quartile 0.8344, median 1.581 and upper quartile 2.708 years.
Estimated payback for waste compaction before collection. Lower quartile 0.8344, median 1.581 and upper quartile 2.708 years. Figure by Industry Applied.

What the records can support

The source lists 710 recommendations under assessment code 3.6193. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 609 comparable records, 179 carry the implemented flag and 405 the non-implemented flag. The remaining 25 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

AS022807

1998

60

12819

0.004680552

AS025006

1999

12256

14688

0.8344227

SD036509

2005

18500

11700

1.581197

HO014703

1997

6500

2400

2.708333

SF031809

2005

16945

4

4236.25

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.108 years. At full forecast savings and a 20% higher installed cost, it would give 1.897 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.