Across 5,178 qualifying US industrial recommendations, the median projected simple payback was 1.6 years. The middle half ran from 0.8591 to 2.712 years. Those figures describe the assessed proposals for variable-speed drive retrofits, in fiscal years 1982 to 2026.

The scope of the plant change

An hourly load profile has more value than the motor nameplate alone. Identify how often the process spends below design duty and what currently controls the flow. Include minimum process flow, control integration and the motor’s operating envelope in the scope.

A recommendation you can reproduce

Recommendation IC032204 in US fiscal year 2025 pairs US$24,421 of implementation cost with US$15,262 in estimated annual net savings. Dividing the first figure by the second gives 1.6 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$10,950 and the median annual saving was US$7,651. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for variable-speed drive retrofits. Lower quartile 0.8591, median 1.6 and upper quartile 2.712 years.
Estimated payback for variable-speed drive retrofits. Lower quartile 0.8591, median 1.6 and upper quartile 2.712 years. Figure by Industry Applied.

What the records can support

The source lists 5,245 recommendations under assessment code 2.4146. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 5,178 comparable records, 1,422 carry the implemented flag and 3,336 the non-implemented flag. The remaining 420 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

SF029007

2004

15

20456

0.0007332812

SF038905

2010

2712

3157

0.8590434

UD096607

2017

613600

383642

1.599408

TT021404

2019

66000

24330

2.7127

SF032209

2006

15259

4

3814.75

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.133 years. At full forecast savings and a 20% higher installed cost, it would give 1.92 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.