Across 14 qualifying US industrial recommendations, the median projected simple payback was 0.3427 years. The middle half ran from 0.1174 to 0.9878 years. Those figures describe the assessed proposals for using utility controlled power management, in fiscal years 1985 to 2018.

The scope of the plant change

Read interval demand and production together. Identify whether the changed quantity is energy, peak demand or a fixed charge before assigning a tariff. Use the same billing boundary across the comparison and allow for coincident loads outside the project.

A recommendation you can reproduce

Recommendation ND028114 in US fiscal year 1997 pairs US$800 of implementation cost with US$2,489 in estimated annual net savings. Dividing the first figure by the second gives 0.3214 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$7,500 and the median annual saving was US$12,463. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for using utility controlled power management. Lower quartile 0.1174, median 0.3427 and upper quartile 0.9878 years.
Estimated payback for using utility controlled power management. Lower quartile 0.1174, median 0.3427 and upper quartile 0.9878 years. Figure by Industry Applied.

What the records can support

The source lists 22 recommendations under assessment code 2.8122. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 14 comparable records, 10 carry the implemented flag and 4 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 7 qualifying records had a median of 0.5151 years. For fiscal years 2000–2014, 6 qualifying records had a median of 0.2446 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

IA023907

2000

125

7353

0.01699986

SF017214

1999

11500

138720

0.08290081

ND028114

1997

800

2489

0.3214142

MA060705

2006

14000

12223

1.145382

AS005402

1992

25000

12703

1.968039

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.4286 years. At full forecast savings and a 20% higher installed cost, it would give 0.3857 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.