Across 24 qualifying US industrial recommendations, the median projected simple payback was 1.269 years. The middle half ran from 0.3564 to 2.413 years. Those figures describe the assessed proposals for using steam condensate for hot water supply (non-potable), in fiscal years 1982 to 2025.

The scope of the plant change

Log steam demand against finished output and record condensate return conditions. Distinguish planned start-up heating from continuous duty and align the baseline with boiler loading. A process change may shift costs between fuel, make-up water and treatment.

A recommendation you can reproduce

Recommendation GT084604 in US fiscal year 2008 pairs US$26,900 of implementation cost with US$17,989 in estimated annual net savings. Dividing the first figure by the second gives 1.495 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$12,082 and the median annual saving was US$17,959. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for using steam condensate for hot water supply (non-potable). Lower quartile 0.3564, median 1.269 and upper quartile 2.413 years.
Estimated payback for using steam condensate for hot water supply (non-potable). Lower quartile 0.3564, median 1.269 and upper quartile 2.413 years. Figure by Industry Applied.

What the records can support

The source lists 24 recommendations under assessment code 2.2128. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 24 comparable records, 11 carry the implemented flag and 13 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 2000–2014, 13 qualifying records had a median of 0.4548 years. For fiscal years 2015–2026, 9 qualifying records had a median of 2.534 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

IA035812

2004

40

3166

0.01263424

UD003403

1982

100

252

0.3968254

GT084604

2008

26900

17989

1.495358

MA053303

2003

25625

10803

2.372026

WV067805

2025

55000

11667

4.714151

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.994 years. At full forecast savings and a 20% higher installed cost, it would give 1.794 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.