The median implementation estimate for using power during off-peak periods was US$1,600 across 87 qualifying US factory recommendations. The middle half of project-cost estimates ran from US$314 to US$7,449.5. These amounts are nominal US dollars from the assessment years.
The scope of the plant change
Read interval demand and production together. Identify whether the changed quantity is energy, peak demand or a fixed charge before assigning a tariff. Use the same billing boundary across the comparison and allow for coincident loads outside the project.
A recommendation you can reproduce
Recommendation BD000401 in US fiscal year 1994 pairs US$1,000 of implementation cost with US$3,162 in estimated annual net savings. Dividing the first figure by the second gives 0.3163 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.
The median implementation cost was US$1,600 and the median annual saving was US$7,700. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

What the records can support
The source lists 197 recommendations under assessment code 2.3137. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.
Of the 87 comparable records, 31 carry the implemented flag and 51 the non-implemented flag. The remaining 5 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.
How the assessment mix affects the comparison
For fiscal years 1980–1999, 27 qualifying records had a median of 0.3163 years. For fiscal years 2000–2014, 29 qualifying records had a median of 0.3955 years. For fiscal years 2015–2026, 31 qualifying records had a median of 0.1443 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.
Worked data
Recommendation ID | US fiscal year | Implementation cost (USD) | Estimated annual net saving (USD) | Recalculated payback (years) |
|---|---|---|---|---|
BD045603 | 2015 | 17 | 5111 | 0.003326159 |
BD048007 | 2016 | 20 | 311 | 0.06430868 |
BD000401 | 1994 | 1000 | 3162 | 0.3162555 |
UU020801 | 2022 | 9500 | 9375 | 1.013333 |
SD054002 | 2017 | 136000 | 33558 | 4.052685 |
Using the evidence in an Australian project
For the worked record, delivering only three quarters of its estimated annual saving would give 0.4217 years. At full forecast savings and a 20% higher installed cost, it would give 0.3795 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.
Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.
What a two-year screening rule would have selected
Among the 87 proposals with a positive implementation cost, 78 (89.655%) had a forecast simple payback of two years or less. The calculation excludes 0 zero-cost records. For a local project with a two-year screening period, divide the quoted installed cost by two to find the minimum annual net saving needed. Use local currency and include the recurring cost of making the change.
Sources and calculation files
The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.