Across 29 qualifying US industrial recommendations, the median projected simple payback was 1.544 years. The middle half ran from 1.1 to 3.038 years. Those figures describe the assessed proposals for using other waste concentration methods, in fiscal years 1994 to 2024.

The scope of the plant change

Follow a measured quantity of material from receiving through saleable output to recovery or disposal. Account for moisture, rework and scrap sold separately. Capture both the unit price and the handling time so a reduced disposal bill is not counted twice.

A recommendation you can reproduce

Recommendation NC010206 in US fiscal year 1996 pairs US$5,000 of implementation cost with US$3,239 in estimated annual net savings. Dividing the first figure by the second gives 1.544 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$14,000 and the median annual saving was US$6,602. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for using other waste concentration methods. Lower quartile 1.1, median 1.544 and upper quartile 3.038 years.
Estimated payback for using other waste concentration methods. Lower quartile 1.1, median 1.544 and upper quartile 3.038 years. Figure by Industry Applied.

What the records can support

The source lists 32 recommendations under assessment code 3.3133. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 29 comparable records, 11 carry the implemented flag and 16 the non-implemented flag. The remaining 2 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 21 qualifying records had a median of 1.476 years. For fiscal years 2015–2026, 6 qualifying records had a median of 2.554 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

WV016009

1999

140

4680

0.02991453

NL007304

2022

1258

1144

1.09965

NC010206

1996

5000

3239

1.543686

SU032408

2012

18000

5924

3.038488

UF011608

1995

4450

447

9.955257

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.058 years. At full forecast savings and a 20% higher installed cost, it would give 1.852 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.