Across 22 qualifying US industrial recommendations, the median projected simple payback was 1.019 years. The middle half ran from 0.5394 to 2.189 years. Those figures describe the assessed proposals for using immersion heating in tanks, melting pots, in fiscal years 1983 to 2024.

The scope of the plant change

Identify the hot and cold sides, the hours at useful temperature and the measured production output. Include periods of standby and cleaning. The gross heat flow and the amount a receiving process can accept are separate quantities in a local estimate.

A recommendation you can reproduce

Recommendation IP019206 in US fiscal year 2024 pairs US$1,105 of implementation cost with US$1,077 in estimated annual net savings. Dividing the first figure by the second gives 1.026 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$13,576 and the median annual saving was US$7,934. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for using immersion heating in tanks, melting pots. Lower quartile 0.5394, median 1.019 and upper quartile 2.189 years.
Estimated payback for using immersion heating in tanks, melting pots. Lower quartile 0.5394, median 1.019 and upper quartile 2.189 years. Figure by Industry Applied.

What the records can support

The source lists 22 recommendations under assessment code 2.2221. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 22 comparable records, 3 carry the implemented flag and 16 the non-implemented flag. The remaining 3 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 12 qualifying records had a median of 1.111 years. For fiscal years 2000–2014, 6 qualifying records had a median of 2.084 years. For fiscal years 2015–2026, 4 qualifying records had a median of 0.6865 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

UF024604

2000

20

584

0.03424658

IP019305

2024

1165

2202

0.5290645

KU051201

1999

31230

30880

1.011334

ND018808

1994

26000

11255

2.310084

KU053602

1999

37800

8260

4.576271

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.368 years. At full forecast savings and a 20% higher installed cost, it would give 1.231 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.