Across 403 qualifying US industrial recommendations, the median projected simple payback was 1.521 years. The middle half ran from 0.8384 to 2.668 years. Those figures describe the assessed proposals for using cooling towers in place of chiller duty, in fiscal years 1984 to 2026.

The scope of the plant change

Compare the process leaving-water requirement with outside wet-bulb conditions and exchanger approach. Count usable hours, fan and pump demand, water treatment and makeup water. Keep the backup chiller available in the costed operating sequence.

A recommendation you can reproduce

Recommendation MA036604 in US fiscal year 1996 pairs US$9,000 of implementation cost with US$5,919 in estimated annual net savings. Dividing the first figure by the second gives 1.521 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$10,800 and the median annual saving was US$7,441. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for using cooling towers in place of chiller duty. Lower quartile 0.8384, median 1.521 and upper quartile 2.668 years.
Estimated payback for using cooling towers in place of chiller duty. Lower quartile 0.8384, median 1.521 and upper quartile 2.668 years. Figure by Industry Applied.

What the records can support

The source lists 416 recommendations under assessment code 2.2614. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 403 comparable records, 90 carry the implemented flag and 294 the non-implemented flag. The remaining 19 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

UD068406

2003

100

4792

0.02086811

NC008406

1996

5100

6221

0.8198039

MA036604

1996

9000

5919

1.520527

MAS02903

2012

22100

8202

2.694465

MU002402

2023

122000

11029.51

11.06123

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.027 years. At full forecast savings and a 20% higher installed cost, it would give 1.825 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.