Across 14 qualifying US industrial recommendations, the median projected simple payback was 1.56 years. The middle half ran from 0.9068 to 2.378 years. Those figures describe the assessed proposals for using cold waste water to cool chiller feed water, in fiscal years 1989 to 2025.

The scope of the plant change

Connect equipment input power to the service delivered. Log entering and leaving conditions plus run status and schedule. Compare matching load or weather bands, since a cooler week can mimic an improvement even when the equipment behaves identically.

A recommendation you can reproduce

Recommendation WV018207 in US fiscal year 2000 pairs US$12,000 of implementation cost with US$7,785 in estimated annual net savings. Dividing the first figure by the second gives 1.541 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$13,250 and the median annual saving was US$14,138. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for using cold waste water to cool chiller feed water. Lower quartile 0.9068, median 1.56 and upper quartile 2.378 years.
Estimated payback for using cold waste water to cool chiller feed water. Lower quartile 0.9068, median 1.56 and upper quartile 2.378 years. Figure by Industry Applied.

What the records can support

The source lists 14 recommendations under assessment code 2.2624. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 14 comparable records, 3 carry the implemented flag and 11 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 7 qualifying records had a median of 1.724 years. For fiscal years 2000–2014, 5 qualifying records had a median of 0.8189 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

AM094507

2025

2650

26500

0.1

SF041903

2012

963

1176

0.8188776

WV018207

2000

12000

7785

1.541426

IA004603

1993

3800

1563

2.431222

UF019703

1998

63950

15069

4.243812

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.055 years. At full forecast savings and a 20% higher installed cost, it would give 1.85 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.