Across 7 qualifying US industrial recommendations, the median projected simple payback was 0.2588 years. The middle half ran from 0.05103 to 2.44 years. Those figures describe the assessed proposals for using absorption, extraction to remove contaminants, in fiscal years 1994 to 1999.

The scope of the plant change

Define the work package in physical terms and identify which meter, production counter or invoice can capture its effect. Record a representative operating cycle before changing the process and retain the underlying unit prices alongside measured quantities.

A recommendation you can reproduce

Recommendation IA013908 in US fiscal year 1996 pairs US$1,018 of implementation cost with US$3,934 in estimated annual net savings. Dividing the first figure by the second gives 0.2588 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$1,018 and the median annual saving was US$9,419. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for using absorption, extraction to remove contaminants. Lower quartile 0.05103, median 0.2588 and upper quartile 2.44 years.
Estimated payback for using absorption, extraction to remove contaminants. Lower quartile 0.05103, median 0.2588 and upper quartile 2.44 years. Figure by Industry Applied.

What the records can support

The source lists 7 recommendations under assessment code 3.3126. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 7 comparable records, 3 carry the implemented flag and 4 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

4 of 7 comparable proposals had an estimated payback of one year or less. 7 carried a positive implementation cost. Inspect zero-cost and positive-cost proposals separately when comparing a change in operating practice with a capital project.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

UL018107

1997

60

5165

0.01161665

OK050301

1996

800

9419

0.08493471

IA013908

1996

1018

3934

0.2587697

OR025506

1995

250000

104000

2.403846

OR020307

1994

636100

189700

3.353189

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.345 years. At full forecast savings and a 20% higher installed cost, it would give 0.3105 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.