The middle half of the estimated payback periods ran from 1.3675 to 3.0835 years for usering battery storage for power quality issues, a spread of 1.716 years. The median among 6 qualifying US proposals was 2.2378 years. Each proposal has equal weight.

The scope of the plant change

Define the work package in physical terms and identify which meter, production counter or invoice can capture its effect. Record a representative operating cycle before changing the process and retain the underlying unit prices alongside measured quantities.

A recommendation you can reproduce

Recommendation SJ005605 in US fiscal year 2026 pairs US$694,340 of implementation cost with US$252,404 in estimated annual net savings. Dividing the first figure by the second gives 2.751 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$370,240 and the median annual saving was US$241,373. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for usering battery storage for power quality issues. Lower quartile 1.367, median 2.238 and upper quartile 3.084 years.
Estimated payback for usering battery storage for power quality issues. Lower quartile 1.367, median 2.238 and upper quartile 3.084 years. Figure by Industry Applied.

What the records can support

The source lists 6 recommendations under assessment code 2.3142. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 6 comparable records, 0 carry the implemented flag and 3 the non-implemented flag. The remaining 3 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

0 of 6 comparable proposals had an estimated payback of one year or less. 6 carried a positive implementation cost. Inspect zero-cost and positive-cost proposals separately when comparing a change in operating practice with a capital project.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

UW231906

2023

871000

750000

1.161333

CW012403

2022

287555

230341.3

1.248387

SF056410

2021

452925

262606

1.724732

UF059504

2023

20000

6261

3.194378

SJ005802

2026

202055

61536

3.283525

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 3.668 years. At full forecast savings and a 20% higher installed cost, it would give 3.301 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

What a two-year screening rule would have selected

Among the 6 proposals with a positive implementation cost, 3 (50%) had a forecast simple payback of two years or less. The calculation excludes 0 zero-cost records. For a local project with a two-year screening period, divide the quoted installed cost by two to find the minimum annual net saving needed. Use local currency and include the recurring cost of making the change.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.