The middle half of the estimated payback periods ran from 0.14126 to 1.6281 years for turning off steam or hot water lines leading to space heating units, a spread of 1.4868 years. The median among 16 qualifying US proposals was 0.59615 years. Each proposal has equal weight.

The scope of the plant change

Log steam demand against finished output and record condensate return conditions. Distinguish planned start-up heating from continuous duty and align the baseline with boiler loading. A process change may shift costs between fuel, make-up water and treatment.

A recommendation you can reproduce

Recommendation UD051405 in US fiscal year 1997 pairs US$1,000 of implementation cost with US$1,589 in estimated annual net savings. Dividing the first figure by the second gives 0.6293 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$2,550 and the median annual saving was US$6,195. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for turning off steam or hot water lines leading to space heating units. Lower quartile 0.1413, median 0.5962 and upper quartile 1.628 years.
Estimated payback for turning off steam or hot water lines leading to space heating units. Lower quartile 0.1413, median 0.5962 and upper quartile 1.628 years. Figure by Industry Applied.

What the records can support

The source lists 25 recommendations under assessment code 2.6213. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 16 comparable records, 5 carry the implemented flag and 10 the non-implemented flag. The remaining 1 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 3 qualifying records had a median of 0.1209 years. For fiscal years 2000–2014, 8 qualifying records had a median of 0.362 years. For fiscal years 2015–2026, 5 qualifying records had a median of 1.773 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

MAS01307

2011

150

2115

0.07092199

NC033902

2006

100000

675393

0.1480619

UD051405

1997

1000

1589

0.6293266

DL007703

2011

100500

63615

1.579816

DL014406

2015

33900

4116

8.236152

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.8391 years. At full forecast savings and a 20% higher installed cost, it would give 0.7552 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

What a two-year screening rule would have selected

Among the 16 proposals with a positive implementation cost, 13 (81.25%) had a forecast simple payback of two years or less. The calculation excludes 0 zero-cost records. For a local project with a two-year screening period, divide the quoted installed cost by two to find the minimum annual net saving needed. Use local currency and include the recurring cost of making the change.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.