The median implementation estimate for storing heated or cooled water for use during peak demand periods was US$123,750 across 24 qualifying US factory recommendations. The middle half of project-cost estimates ran from US$36,519.5 to US$203,356.2. These amounts are nominal US dollars from the assessment years.

The scope of the plant change

Read interval demand and production together. Identify whether the changed quantity is energy, peak demand or a fixed charge before assigning a tariff. Use the same billing boundary across the comparison and allow for coincident loads outside the project.

A recommendation you can reproduce

Recommendation CI004705 in US fiscal year 2025 pairs US$135,900 of implementation cost with US$44,384 in estimated annual net savings. Dividing the first figure by the second gives 3.062 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$123,750 and the median annual saving was US$27,144. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for storing heated or cooled water for use during peak demand periods. Lower quartile 1.781, median 3.208 and upper quartile 7.208 years.
Estimated payback for storing heated or cooled water for use during peak demand periods. Lower quartile 1.781, median 3.208 and upper quartile 7.208 years. Figure by Industry Applied.

What the records can support

The source lists 25 recommendations under assessment code 2.3112. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 24 comparable records, 3 carry the implemented flag and 18 the non-implemented flag. The remaining 3 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 6 qualifying records had a median of 2.374 years. For fiscal years 2000–2014, 4 qualifying records had a median of 5.924 years. For fiscal years 2015–2026, 14 qualifying records had a median of 3.402 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

UU025905

2024

33000

53643.1

0.615177

MI041902

2023

37026

19853

1.865008

CI003103

2024

30000

8942

3.354954

UC231413

2023

170000

24735.05

6.872838

UF029605

2002

202500

13799

14.67498

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 4.083 years. At full forecast savings and a 20% higher installed cost, it would give 3.674 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

What a two-year screening rule would have selected

Among the 24 proposals with a positive implementation cost, 7 (29.167%) had a forecast simple payback of two years or less. The calculation excludes 0 zero-cost records. For a local project with a two-year screening period, divide the quoted installed cost by two to find the minimum annual net saving needed. Use local currency and include the recurring cost of making the change.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.