Across 41 qualifying US industrial recommendations, the median projected simple payback was 0.2611 years. The middle half ran from 0.09708 to 0.8026 years. Those figures describe the assessed proposals for shifting from daytime to nighttime operation, in fiscal years 1990 to 2025.

The scope of the plant change

Define the work package in physical terms and identify which meter, production counter or invoice can capture its effect. Record a representative operating cycle before changing the process and retain the underlying unit prices alongside measured quantities.

A recommendation you can reproduce

Recommendation AM070305 in US fiscal year 2016 pairs US$1,000 of implementation cost with US$3,830 in estimated annual net savings. Dividing the first figure by the second gives 0.2611 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$2,700 and the median annual saving was US$6,810. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for shifting from daytime to nighttime operation. Lower quartile 0.09708, median 0.2611 and upper quartile 0.8026 years.
Estimated payback for shifting from daytime to nighttime operation. Lower quartile 0.09708, median 0.2611 and upper quartile 0.8026 years. Figure by Industry Applied.

What the records can support

The source lists 126 recommendations under assessment code 2.3134. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 41 comparable records, 9 carry the implemented flag and 30 the non-implemented flag. The remaining 2 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 11 qualifying records had a median of 0.3342 years. For fiscal years 2000–2014, 24 qualifying records had a median of 0.1701 years. For fiscal years 2015–2026, 6 qualifying records had a median of 1.052 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

BD033308

2007

2

66946

2.987482e-05

NC030501

2004

3500

36051

0.09708469

AM070305

2016

1000

3830

0.2610966

LE027603

2008

30600

38127

0.8025808

OK056101

1998

5000

2306

2.168257

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.3481 years. At full forecast savings and a 20% higher installed cost, it would give 0.3133 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.