Across 9 qualifying US industrial recommendations, the median projected simple payback was 0.3652 years. The middle half ran from 0.1164 to 0.5647 years. Those figures describe the assessed proposals for revising raw material specs, in fiscal years 1995 to 2019.

The scope of the plant change

Follow a measured quantity of material from receiving through saleable output to recovery or disposal. Account for moisture, rework and scrap sold separately. Capture both the unit price and the handling time so a reduced disposal bill is not counted twice.

A recommendation you can reproduce

Recommendation AM024709 in US fiscal year 1995 pairs US$30,200 of implementation cost with US$82,700 in estimated annual net savings. Dividing the first figure by the second gives 0.3652 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$30,200 and the median annual saving was US$82,700. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

What the records can support

The source lists 14 recommendations under assessment code 3.1172. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 9 comparable records, 3 carry the implemented flag and 6 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

7 of 9 comparable proposals had an estimated payback of one year or less. 9 carried a positive implementation cost. Inspect zero-cost and positive-cost proposals separately when comparing a change in operating practice with a capital project.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

BD047109

2015

7000

90750

0.07713499

WV010811

1997

4293

36895

0.1163572

AM024709

1995

30200

82700

0.3651753

LE024702

2006

60000

106250

0.5647059

OR028701

1997

104000

32300

3.219814

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.4869 years. At full forecast savings and a 20% higher installed cost, it would give 0.4382 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.