The median implementation estimate for replacing unnecessary compressed-air uses was US$1,550.5 across 2,400 qualifying US factory recommendations. The middle half of project-cost estimates ran from US$500 to US$4,996.2. These amounts are nominal US dollars from the assessment years.
The scope of the plant change
Survey end uses individually. Compare the existing process with a blower or mechanical alternative at the same finished quality and cycle rate. The compressor will only save the electricity that its control sequence allows it to shed.
A recommendation you can reproduce
Recommendation GT076601 in US fiscal year 2003 pairs US$500 of implementation cost with US$770 in estimated annual net savings. Dividing the first figure by the second gives 0.6494 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.
The median implementation cost was US$1,550 and the median annual saving was US$2,944. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

What the records can support
The source lists 2,709 recommendations under assessment code 2.4239. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.
Of the 2,400 comparable records, 1,019 carry the implemented flag and 1,246 the non-implemented flag. The remaining 135 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.
Worked data
Recommendation ID | US fiscal year | Implementation cost (USD) | Estimated annual net saving (USD) | Recalculated payback (years) |
|---|---|---|---|---|
SF029005 | 2004 | 4 | 15496 | 0.0002581311 |
MI010908 | 2005 | 156 | 685 | 0.2277372 |
GT076601 | 2003 | 500 | 770 | 0.6493506 |
SF006004 | 1995 | 1291 | 876 | 1.473744 |
UC260404 | 2025 | 245025 | 12718 | 19.266 |
Using the evidence in an Australian project
For the worked record, delivering only three quarters of its estimated annual saving would give 0.8658 years. At full forecast savings and a 20% higher installed cost, it would give 0.7792 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.
Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.
What a two-year screening rule would have selected
Among the 2,400 proposals with a positive implementation cost, 1,995 (83.125%) had a forecast simple payback of two years or less. The calculation excludes 0 zero-cost records. For a local project with a two-year screening period, divide the quoted installed cost by two to find the minimum annual net saving needed. Use local currency and include the recurring cost of making the change.
Sources and calculation files
The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.