Across 10 qualifying US industrial recommendations, the median projected simple payback was 1.665 years. The middle half ran from 1.037 to 2.899 years. Those figures describe the assessed proposals for replacing electric reheat with heat pipes, in fiscal years 1993 to 2020.

The scope of the plant change

Read interval demand and production together. Identify whether the changed quantity is energy, peak demand or a fixed charge before assigning a tariff. Use the same billing boundary across the comparison and allow for coincident loads outside the project.

A recommendation you can reproduce

Recommendation UF010708 in US fiscal year 1995 pairs US$31,500 of implementation cost with US$18,904 in estimated annual net savings. Dividing the first figure by the second gives 1.666 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$20,500 and the median annual saving was US$11,300. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for replacing electric reheat with heat pipes. Lower quartile 1.037, median 1.665 and upper quartile 2.899 years.
Estimated payback for replacing electric reheat with heat pipes. Lower quartile 1.037, median 1.665 and upper quartile 2.899 years. Figure by Industry Applied.

What the records can support

The source lists 10 recommendations under assessment code 2.7271. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 10 comparable records, 1 carry the implemented flag and 9 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

1 of 10 comparable proposals had an estimated payback of one year or less. 10 carried a positive implementation cost. Inspect zero-cost and positive-cost proposals separately when comparing a change in operating practice with a capital project.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

UF005406

1993

7000

11340

0.617284

UF005509

1993

22500

21866

1.028995

UF012003

1995

3500

2103

1.664289

UF008508

1994

2400

760

3.157895

NL004601

2020

20000

5384

3.71471

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.222 years. At full forecast savings and a 20% higher installed cost, it would give 2 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.