Across 26 qualifying US industrial recommendations, the median projected simple payback was 1.285 years. The middle half ran from 0.8454 to 2.297 years. Those figures describe the assessed proposals for replacing electric motor with fossil fuel engine, in fiscal years 1994 to 2016.

The scope of the plant change

Read interval demand and production together. Identify whether the changed quantity is energy, peak demand or a fixed charge before assigning a tariff. Use the same billing boundary across the comparison and allow for coincident loads outside the project.

A recommendation you can reproduce

Recommendation AR002607 in US fiscal year 1994 pairs US$30,500 of implementation cost with US$22,438 in estimated annual net savings. Dividing the first figure by the second gives 1.359 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$32,500 and the median annual saving was US$21,942. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for replacing electric motor with fossil fuel engine. Lower quartile 0.8454, median 1.285 and upper quartile 2.297 years.
Estimated payback for replacing electric motor with fossil fuel engine. Lower quartile 0.8454, median 1.285 and upper quartile 2.297 years. Figure by Industry Applied.

What the records can support

The source lists 28 recommendations under assessment code 2.4134. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 26 comparable records, 2 carry the implemented flag and 22 the non-implemented flag. The remaining 2 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 13 qualifying records had a median of 0.9723 years. For fiscal years 2000–2014, 12 qualifying records had a median of 2.237 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

MA071006

2013

1000

3796

0.2634352

NC043409

2011

876

1039

0.8431184

SD047104

2013

96000

79351

1.209815

TT008603

2012

7500

3238

2.316245

SF009205

1996

129300

9436

13.70284

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.812 years. At full forecast savings and a 20% higher installed cost, it would give 1.631 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.