Across 17 qualifying US industrial recommendations, the median projected simple payback was 0.7463 years. The middle half ran from 0.4425 to 0.9346 years. Those figures describe the assessed proposals for removing rollers from the machines and clean in a closed solvent cleaner, in fiscal years 1994 to 2005.

The scope of the plant change

Define the work package in physical terms and identify which meter, production counter or invoice can capture its effect. Record a representative operating cycle before changing the process and retain the underlying unit prices alongside measured quantities.

A recommendation you can reproduce

Recommendation CO035608 in US fiscal year 1996 pairs US$1,000 of implementation cost with US$1,340 in estimated annual net savings. Dividing the first figure by the second gives 0.7463 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$1,150 and the median annual saving was US$2,210. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for removing rollers from the machines and clean in a closed solvent cleaner. Lower quartile 0.4425, median 0.7463 and upper quartile 0.9346 years.
Estimated payback for removing rollers from the machines and clean in a closed solvent cleaner. Lower quartile 0.4425, median 0.7463 and upper quartile 0.9346 years. Figure by Industry Applied.

What the records can support

The source lists 17 recommendations under assessment code 3.8125. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 17 comparable records, 5 carry the implemented flag and 12 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 13 qualifying records had a median of 0.7463 years. For fiscal years 2000–2014, 4 qualifying records had a median of 0.526 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

CO054801

2004

1150

16080

0.07151741

CO036202

1996

1000

2260

0.4424779

CO035608

1996

1000

1340

0.7462687

CO033803

1995

1000

1070

0.9345794

CO037304

1996

1000

520

1.923077

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.995 years. At full forecast savings and a 20% higher installed cost, it would give 0.8955 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.