Across 17 qualifying US industrial recommendations, the median projected simple payback was 1.143 years. The middle half ran from 0.5486 to 2.021 years. Those figures describe the assessed proposals for recycling waste ink and cleanup solvent, in fiscal years 1994 to 2006.

The scope of the plant change

Follow a measured quantity of material from receiving through saleable output to recovery or disposal. Account for moisture, rework and scrap sold separately. Capture both the unit price and the handling time so a reduced disposal bill is not counted twice.

A recommendation you can reproduce

Recommendation NC028901 in US fiscal year 2004 pairs US$25,000 of implementation cost with US$21,873 in estimated annual net savings. Dividing the first figure by the second gives 1.143 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$6,150 and the median annual saving was US$11,210. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for recycling waste ink and cleanup solvent. Lower quartile 0.5486, median 1.143 and upper quartile 2.021 years.
Estimated payback for recycling waste ink and cleanup solvent. Lower quartile 0.5486, median 1.143 and upper quartile 2.021 years. Figure by Industry Applied.

What the records can support

The source lists 31 recommendations under assessment code 3.5121. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 17 comparable records, 7 carry the implemented flag and 9 the non-implemented flag. The remaining 1 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 14 qualifying records had a median of 1.008 years. For fiscal years 2000–2014, 3 qualifying records had a median of 1.389 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

MO017205

1996

500

10800

0.0462963

CO031901

1994

6150

11210

0.5486173

NC028901

2004

25000

21873

1.142962

UL014005

1995

11265

5575

2.020628

UM008604

1997

5080

1270

4

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.524 years. At full forecast savings and a 20% higher installed cost, it would give 1.372 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.