Across 35 qualifying US industrial recommendations, the median projected simple payback was 1.322 years. The middle half ran from 0.6281 to 2.02 years. Those figures describe the assessed proposals for recycling cleaning solvent and reusing, in fiscal years 1994 to 2009.

The scope of the plant change

Follow a measured quantity of material from receiving through saleable output to recovery or disposal. Account for moisture, rework and scrap sold separately. Capture both the unit price and the handling time so a reduced disposal bill is not counted twice.

A recommendation you can reproduce

Recommendation OR034309 in US fiscal year 1999 pairs US$6,000 of implementation cost with US$4,540 in estimated annual net savings. Dividing the first figure by the second gives 1.322 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$7,700 and the median annual saving was US$5,850. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for recycling cleaning solvent and reusing. Lower quartile 0.6281, median 1.322 and upper quartile 2.02 years.
Estimated payback for recycling cleaning solvent and reusing. Lower quartile 0.6281, median 1.322 and upper quartile 2.02 years. Figure by Industry Applied.

What the records can support

The source lists 39 recommendations under assessment code 3.8143. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 35 comparable records, 14 carry the implemented flag and 20 the non-implemented flag. The remaining 1 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 30 qualifying records had a median of 1.237 years. For fiscal years 2000–2014, 5 qualifying records had a median of 1.874 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

SD015207

1996

50

5625

0.008888889

SD023509

1999

20000

34580

0.578369

OR034309

1999

6000

4540

1.321586

UL017707

1997

9226

4260

2.165728

OK050907

1996

6901

600

11.50167

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.762 years. At full forecast savings and a 20% higher installed cost, it would give 1.586 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.