Across 274 qualifying US industrial recommendations, the median projected simple payback was 0.8519 years. The middle half ran from 0.3827 to 1.638 years. Those figures describe the assessed proposals for recovery and reuse of cooling water, in fiscal years 1984 to 2026.

The scope of the plant change

Record the temperature and volume of the available stream through the production cycle. Identify the receiving use, its timing and quality requirement. Include storage and transfer in the cost where source and sink peak at different times.

A recommendation you can reproduce

Recommendation BD008907 in US fiscal year 1997 pairs US$4,500 of implementation cost with US$5,285 in estimated annual net savings. Dividing the first figure by the second gives 0.8515 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$5,000 and the median annual saving was US$6,149. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for recovery and reuse of cooling water. Lower quartile 0.3827, median 0.8519 and upper quartile 1.638 years.
Estimated payback for recovery and reuse of cooling water. Lower quartile 0.3827, median 0.8519 and upper quartile 1.638 years. Figure by Industry Applied.

What the records can support

The source lists 304 recommendations under assessment code 3.4115. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 274 comparable records, 120 carry the implemented flag and 148 the non-implemented flag. The remaining 6 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

MA024101

1992

1

15035

6.651147e-05

GT056302

1995

14400

37645

0.3825209

BD008907

1997

4500

5285

0.8514664

SF026210

2003

6871

4190

1.639857

LE015906

2003

25500

1286

19.82893

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.135 years. At full forecast savings and a 20% higher installed cost, it would give 1.022 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.