Across 247 qualifying US industrial recommendations, the median projected simple payback was 0.2018 years. The middle half ran from 0.06265 to 0.6065 years. Those figures describe the assessed proposals for purchasing gas directly from a contract gas supplier, in fiscal years 1987 to 2026.

The scope of the plant change

Define the work package in physical terms and identify which meter, production counter or invoice can capture its effect. Record a representative operating cycle before changing the process and retain the underlying unit prices alongside measured quantities.

A recommendation you can reproduce

Recommendation CO014101 in US fiscal year 1989 pairs US$6,700 of implementation cost with US$33,200 in estimated annual net savings. Dividing the first figure by the second gives 0.2018 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$2,000 and the median annual saving was US$14,608. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for purchasing gas directly from a contract gas supplier. Lower quartile 0.06265, median 0.2018 and upper quartile 0.6065 years.
Estimated payback for purchasing gas directly from a contract gas supplier. Lower quartile 0.06265, median 0.2018 and upper quartile 0.6065 years. Figure by Industry Applied.

What the records can support

The source lists 348 recommendations under assessment code 2.8113. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 247 comparable records, 101 carry the implemented flag and 134 the non-implemented flag. The remaining 12 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 195 qualifying records had a median of 0.203 years. For fiscal years 2000–2014, 27 qualifying records had a median of 0.08547 years. For fiscal years 2015–2026, 25 qualifying records had a median of 0.5479 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

LE025501

2007

500

433831

0.001152523

CO019901

1990

6000

95700

0.06269592

CO014101

1989

6700

33200

0.2018072

MA028601

1993

19668

32481

0.6055232

GT062701

1997

173400

26200

6.618321

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.2691 years. At full forecast savings and a 20% higher installed cost, it would give 0.2422 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.