Across 181 qualifying US industrial recommendations, the median projected simple payback was 1.265 years. The middle half ran from 0.6132 to 2.6 years. Those figures describe the assessed proposals for preheating boiler makeup water with waste process heat, in fiscal years 1981 to 2026.

The scope of the plant change

Log steam demand against finished output and record condensate return conditions. Distinguish planned start-up heating from continuous duty and align the baseline with boiler loading. A process change may shift costs between fuel, make-up water and treatment.

A recommendation you can reproduce

Recommendation LE046202 in US fiscal year 2018 pairs US$20,000 of implementation cost with US$15,808 in estimated annual net savings. Dividing the first figure by the second gives 1.265 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$8,930 and the median annual saving was US$8,821. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for preheating boiler makeup water with waste process heat. Lower quartile 0.6132, median 1.265 and upper quartile 2.6 years.
Estimated payback for preheating boiler makeup water with waste process heat. Lower quartile 0.6132, median 1.265 and upper quartile 2.6 years. Figure by Industry Applied.

What the records can support

The source lists 184 recommendations under assessment code 2.2441. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 181 comparable records, 47 carry the implemented flag and 128 the non-implemented flag. The remaining 6 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 77 qualifying records had a median of 1.218 years. For fiscal years 2000–2014, 57 qualifying records had a median of 0.8791 years. For fiscal years 2015–2026, 47 qualifying records had a median of 2.712 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

OK071301

2005

1436

81171

0.01769105

UD018602

1986

2812

4586

0.6131705

LE046202

2018

20000

15808

1.265182

SD061107

2021

6000

2308

2.599653

DL025507

2025

25000

3100

8.064516

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.687 years. At full forecast savings and a 20% higher installed cost, it would give 1.518 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.