Across 279 qualifying US industrial recommendations, the median projected simple payback was 0.3085 years. The middle half ran from 0.1352 to 0.9497 years. Those figures describe the assessed proposals for predictive maintenance programmes, in fiscal years 1999 to 2026.

The scope of the plant change

Identify failure modes with a measurable precursor and record the current cost of downtime and remedial work. Estimate how many events the programme can detect in time. Include sensor support, analyst time and work-order follow-through.

A recommendation you can reproduce

Recommendation WV054905 in US fiscal year 2017 pairs US$1,000 of implementation cost with US$3,241 in estimated annual net savings. Dividing the first figure by the second gives 0.3085 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$1,000 and the median annual saving was US$4,560. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for predictive maintenance programmes. Lower quartile 0.1352, median 0.3085 and upper quartile 0.9497 years.
Estimated payback for predictive maintenance programmes. Lower quartile 0.1352, median 0.3085 and upper quartile 0.9497 years. Figure by Industry Applied.

What the records can support

The source lists 282 recommendations under assessment code 2.4157. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 279 comparable records, 235 carry the implemented flag and 35 the non-implemented flag. The remaining 9 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

WV051904

2016

1000

45119

0.02216361

WV022206

2001

1792

13220

0.1355522

WV054905

2017

1000

3241

0.3085467

WV043205

2011

2000

2144

0.9328358

WV021508

2001

780

97

8.041237

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.4114 years. At full forecast savings and a 20% higher installed cost, it would give 0.3703 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.

Cover photograph by Mikhail Nilov, via Pexels. The photograph illustrates the subject. Industry Applied produced the figure and calculations from the linked source.