Across 19 qualifying US industrial recommendations, the median projected simple payback was 1.316 years. The middle half ran from 0.6562 to 2.7 years. Those figures describe the assessed proposals for modifying dye beck, in fiscal years 1982 to 2002.
The scope of the plant change
Define the work package in physical terms and identify which meter, production counter or invoice can capture its effect. Record a representative operating cycle before changing the process and retain the underlying unit prices alongside measured quantities.
A recommendation you can reproduce
Recommendation GT020105 in US fiscal year 1983 pairs US$51,000 of implementation cost with US$38,740 in estimated annual net savings. Dividing the first figure by the second gives 1.316 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.
The median implementation cost was US$41,000 and the median annual saving was US$22,904. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.
What the records can support
The source lists 23 recommendations under assessment code 2.5191. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.
Of the 19 comparable records, 7 carry the implemented flag and 12 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.
How the assessment mix affects the comparison
6 of 19 comparable proposals had an estimated payback of one year or less. 19 carried a positive implementation cost. Inspect zero-cost and positive-cost proposals separately when comparing a change in operating practice with a capital project.
Worked data
Recommendation ID | US fiscal year | Implementation cost (USD) | Estimated annual net saving (USD) | Recalculated payback (years) |
|---|---|---|---|---|
GT025009 | 1985 | 45000 | 146000 | 0.3082192 |
MO000101 | 1990 | 16000 | 30784 | 0.5197505 |
GT020105 | 1983 | 51000 | 38740 | 1.316469 |
GT073112 | 2002 | 73150 | 22904 | 3.193765 |
GT020904 | 1984 | 60000 | 7435 | 8.069939 |
Using the evidence in an Australian project
For the worked record, delivering only three quarters of its estimated annual saving would give 1.755 years. At full forecast savings and a 20% higher installed cost, it would give 1.58 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.
Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.
Sources and calculation files
The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.