Across 326 qualifying US industrial recommendations, the median projected simple payback was 0.3347 years. The middle half ran from 0.1468 to 0.7737 years. Those figures describe the assessed proposals for metering recycled industrial water, in fiscal years 1988 to 2026.

The scope of the plant change

Choose a boundary that distinguishes recovered water from mains makeup and discharge. Check the local utility’s metering and charging basis before assigning a credit. Use coincident readings to reconcile the water balance across several shifts.

A recommendation you can reproduce

Recommendation UD079307 in US fiscal year 2009 pairs US$1,000 of implementation cost with US$2,970 in estimated annual net savings. Dividing the first figure by the second gives 0.3367 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$1,390 and the median annual saving was US$4,467. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for metering recycled industrial water. Lower quartile 0.1468, median 0.3347 and upper quartile 0.7737 years.
Estimated payback for metering recycled industrial water. Lower quartile 0.1468, median 0.3347 and upper quartile 0.7737 years. Figure by Industry Applied.

What the records can support

The source lists 367 recommendations under assessment code 3.4116. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 326 comparable records, 109 carry the implemented flag and 198 the non-implemented flag. The remaining 19 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

TT028701

2023

60

23724

0.002529084

UK140315

2014

5000

34100

0.1466276

UF041710

2008

15000

45096

0.3326237

IP012609

2019

1356

1752

0.7739726

MS025907

2004

245000

5481

44.69987

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.4489 years. At full forecast savings and a 20% higher installed cost, it would give 0.404 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.