Across 42 qualifying US industrial recommendations, the median projected simple payback was 2.944 years. The middle half ran from 1.704 to 5.041 years. Those figures describe the assessed proposals for making ice during off peak hours for cooling, in fiscal years 1994 to 2026.

The scope of the plant change

Read interval demand and production together. Identify whether the changed quantity is energy, peak demand or a fixed charge before assigning a tariff. Use the same billing boundary across the comparison and allow for coincident loads outside the project.

A recommendation you can reproduce

Recommendation MO011201 in US fiscal year 1994 pairs US$33,300 of implementation cost with US$11,331 in estimated annual net savings. Dividing the first figure by the second gives 2.939 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$74,165 and the median annual saving was US$27,180. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for making ice during off peak hours for cooling. Lower quartile 1.704, median 2.944 and upper quartile 5.041 years.
Estimated payback for making ice during off peak hours for cooling. Lower quartile 1.704, median 2.944 and upper quartile 5.041 years. Figure by Industry Applied.

What the records can support

The source lists 44 recommendations under assessment code 2.3113. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 42 comparable records, 6 carry the implemented flag and 33 the non-implemented flag. The remaining 3 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 9 qualifying records had a median of 2.161 years. For fiscal years 2000–2014, 18 qualifying records had a median of 3.421 years. For fiscal years 2015–2026, 15 qualifying records had a median of 2.949 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

AS045405

2018

150

11530

0.01300954

UF059301

2023

215600

131807

1.635725

MO011201

1994

33300

11331

2.93884

OK087004

2013

105120

20022

5.250225

SF033513

2006

912000

87302

10.4465

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 3.918 years. At full forecast savings and a 20% higher installed cost, it would give 3.527 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.