Across 38 qualifying US industrial recommendations, the median projected simple payback was 1.364 years. The middle half ran from 0.5556 to 2.141 years. Those figures describe the assessed proposals for making a new by-product, in fiscal years 1994 to 2024.

The scope of the plant change

Connect equipment input power to the service delivered. Log entering and leaving conditions plus run status and schedule. Compare matching load or weather bands, since a cooler week can mimic an improvement even when the equipment behaves identically.

A recommendation you can reproduce

Recommendation OK109313 in US fiscal year 2023 pairs US$1,600,000 of implementation cost with US$1,221,405 in estimated annual net savings. Dividing the first figure by the second gives 1.31 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$100,000 and the median annual saving was US$98,400. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for making a new by-product. Lower quartile 0.5556, median 1.364 and upper quartile 2.141 years.
Estimated payback for making a new by-product. Lower quartile 0.5556, median 1.364 and upper quartile 2.141 years. Figure by Industry Applied.

What the records can support

The source lists 44 recommendations under assessment code 3.1182. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 38 comparable records, 9 carry the implemented flag and 25 the non-implemented flag. The remaining 4 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 14 qualifying records had a median of 1.67 years. For fiscal years 2000–2014, 17 qualifying records had a median of 1.05 years. For fiscal years 2015–2026, 7 qualifying records had a median of 1.31 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

LM006108

2003

300

20000

0.015

TN058301

1996

390800

723960

0.5398088

OK109313

2023

1600000

1221405

1.309967

TN056311

1995

100000

45294

2.207798

TN053010

1994

988447

100000

9.88447

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.747 years. At full forecast savings and a 20% higher installed cost, it would give 1.572 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.