Across 19,516 qualifying US industrial recommendations, the median projected simple payback was 1.688 years. The middle half ran from 0.8523 to 2.835 years. Those figures describe the assessed proposals for lighting retrofits, in fiscal years 1981 to 2026.

The scope of the plant change

Count fittings by circuit and record switching hours in each shift. A fitting in an intermittently used store has a different opportunity from the same fitting over a three-shift line. Compare metered circuit demand at equivalent light output.

A recommendation you can reproduce

Recommendation ND018904 in US fiscal year 1994 pairs US$650 of implementation cost with US$385 in estimated annual net savings. Dividing the first figure by the second gives 1.688 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$4,096 and the median annual saving was US$2,528. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for lighting retrofits. Lower quartile 0.8523, median 1.688 and upper quartile 2.835 years.
Estimated payback for lighting retrofits. Lower quartile 0.8523, median 1.688 and upper quartile 2.835 years. Figure by Industry Applied.

What the records can support

The source lists 20,327 recommendations under assessment code 2.7142. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 19,516 comparable records, 10,629 carry the implemented flag and 7,992 the non-implemented flag. The remaining 895 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

GT087901

2011

1

6235.17

0.0001603806

UF025909

2000

600

704

0.8522727

ND018904

1994

650

385

1.688312

GT060303

1996

3036

1071

2.834734

SF031805

2005

11928

3

3976

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.251 years. At full forecast savings and a 20% higher installed cost, it would give 2.026 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.