Across 150 qualifying US industrial recommendations, the median projected simple payback was 0.4658 years. The middle half ran from 0.1924 to 1.034 years. Those figures describe the assessed proposals for isolating redundant compressed-air branches, in fiscal years 1984 to 2026.

The scope of the plant change

Trace both ends of the branch and identify any intermittent uses. Compare station power and pressure over similar idle periods with the branch isolated and connected. Flag work that changes receiver volume or peak pressure stability.

A recommendation you can reproduce

Recommendation UF043707 in US fiscal year 2010 pairs US$1,979 of implementation cost with US$4,197 in estimated annual net savings. Dividing the first figure by the second gives 0.4715 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$1,204 and the median annual saving was US$2,639. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for isolating redundant compressed-air branches. Lower quartile 0.1924, median 0.4658 and upper quartile 1.034 years.
Estimated payback for isolating redundant compressed-air branches. Lower quartile 0.1924, median 0.4658 and upper quartile 1.034 years. Figure by Industry Applied.

What the records can support

The source lists 204 recommendations under assessment code 2.4235. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 150 comparable records, 77 carry the implemented flag and 65 the non-implemented flag. The remaining 8 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

TT015606

2015

13

1454

0.008940853

TA008001

2004

13000

67776

0.1918083

UF037802

2006

5044

10965

0.4600091

MA001502

1985

1035

991

1.0444

MA055208

2004

18000

428

42.05607

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.6287 years. At full forecast savings and a 20% higher installed cost, it would give 0.5658 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.