Across 29 qualifying US industrial recommendations, the median projected simple payback was 6.166 years. The middle half ran from 3.762 to 8.577 years. Those figures describe the assessed proposals for installing wind powered electric generator, in fiscal years 2002 to 2026.

The scope of the plant change

Read interval demand and production together. Identify whether the changed quantity is energy, peak demand or a fixed charge before assigning a tariff. Use the same billing boundary across the comparison and allow for coincident loads outside the project.

A recommendation you can reproduce

Recommendation TR001706 in US fiscal year 2019 pairs US$831,480 of implementation cost with US$134,851 in estimated annual net savings. Dividing the first figure by the second gives 6.166 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$1,153,710 and the median annual saving was US$148,851. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for installing wind powered electric generator. Lower quartile 3.762, median 6.166 and upper quartile 8.577 years.
Estimated payback for installing wind powered electric generator. Lower quartile 3.762, median 6.166 and upper quartile 8.577 years. Figure by Industry Applied.

What the records can support

The source lists 31 recommendations under assessment code 2.9121. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 29 comparable records, 4 carry the implemented flag and 23 the non-implemented flag. The remaining 2 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 2000–2014, 15 qualifying records had a median of 7.603 years. For fiscal years 2015–2026, 14 qualifying records had a median of 5.707 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

UD082304

2010

1400000

1820272

0.7691158

LS242104

2024

560000

148851

3.762151

TR001706

2019

831480

134851

6.165916

AS047601

2019

7925140

924031

8.576704

CO064607

2011

5260

270

19.48148

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 8.221 years. At full forecast savings and a 20% higher installed cost, it would give 7.399 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.