The middle half of the estimated payback periods ran from 0.61598 to 1.7769 years for installing spectral reflectors or delamp, a spread of 1.1609 years. The median among 470 qualifying US proposals was 1.119 years. Each proposal has equal weight.

The scope of the plant change

Record the circuit load, lighting hours and the actual visual task in the work area. Use separately controlled zones as measurement boundaries. Keep a record of daylight, shift occupancy and any maintenance intervention between the baseline and follow-up periods.

A recommendation you can reproduce

Recommendation WV018505 in US fiscal year 2000 pairs US$4,872 of implementation cost with US$4,368 in estimated annual net savings. Dividing the first figure by the second gives 1.115 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$3,489 and the median annual saving was US$3,039. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for installing spectral reflectors or delamp. Lower quartile 0.616, median 1.119 and upper quartile 1.777 years.
Estimated payback for installing spectral reflectors or delamp. Lower quartile 0.616, median 1.119 and upper quartile 1.777 years. Figure by Industry Applied.

What the records can support

The source lists 517 recommendations under assessment code 2.7144. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 470 comparable records, 201 carry the implemented flag and 248 the non-implemented flag. The remaining 21 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 293 qualifying records had a median of 1.232 years. For fiscal years 2000–2014, 121 qualifying records had a median of 0.9423 years. For fiscal years 2015–2026, 56 qualifying records had a median of 0.4516 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

OK064402

2002

3

570

0.005263158

SF007402

1995

5369

8747

0.6138104

WV018505

2000

4872

4368

1.115385

SD013405

1996

5520

3101

1.780071

UF002602

1992

17100

579

29.53368

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.487 years. At full forecast savings and a 20% higher installed cost, it would give 1.338 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

What a two-year screening rule would have selected

Among the 470 proposals with a positive implementation cost, 373 (79.362%) had a forecast simple payback of two years or less. The calculation excludes 0 zero-cost records. For a local project with a two-year screening period, divide the quoted installed cost by two to find the minimum annual net saving needed. Use local currency and include the recurring cost of making the change.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.