Across 76 qualifying US industrial recommendations, the median projected simple payback was 1.73 years. The middle half ran from 0.7252 to 3.202 years. Those figures describe the assessed proposals for installing smaller boiler (increase high fire duty cycle), in fiscal years 1991 to 2025.

The scope of the plant change

Log steam demand against finished output and record condensate return conditions. Distinguish planned start-up heating from continuous duty and align the baseline with boiler loading. A process change may shift costs between fuel, make-up water and treatment.

A recommendation you can reproduce

Recommendation NC022705 in US fiscal year 2001 pairs US$50,000 of implementation cost with US$30,612 in estimated annual net savings. Dividing the first figure by the second gives 1.633 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$27,500 and the median annual saving was US$19,013. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for installing smaller boiler (increase high fire duty cycle). Lower quartile 0.7252, median 1.73 and upper quartile 3.202 years.
Estimated payback for installing smaller boiler (increase high fire duty cycle). Lower quartile 0.7252, median 1.73 and upper quartile 3.202 years. Figure by Industry Applied.

What the records can support

The source lists 80 recommendations under assessment code 2.1223. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 76 comparable records, 20 carry the implemented flag and 51 the non-implemented flag. The remaining 5 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 27 qualifying records had a median of 1.48 years. For fiscal years 2000–2014, 30 qualifying records had a median of 1.553 years. For fiscal years 2015–2026, 19 qualifying records had a median of 2.906 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

BD038002

2010

11

6928

0.00158776

TN052308

1994

16000

21222

0.7539346

MA065302

2009

68000

37210

1.827466

OR036003

1999

20000

6248

3.201024

OR078801

2024

2500000

126866

19.70583

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.178 years. At full forecast savings and a 20% higher installed cost, it would give 1.96 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.