Across 68 qualifying US industrial recommendations, the median projected simple payback was 1.89 years. The middle half ran from 0.429 to 3.71 years. Those figures describe the assessed proposals for installing equipment to utilize waste fuel, in fiscal years 2002 to 2025.

The scope of the plant change

Follow a measured quantity of material from receiving through saleable output to recovery or disposal. Account for moisture, rework and scrap sold separately. Capture both the unit price and the handling time so a reduced disposal bill is not counted twice.

A recommendation you can reproduce

Recommendation BS003603 in US fiscal year 2014 pairs US$31,134 of implementation cost with US$16,582 in estimated annual net savings. Dividing the first figure by the second gives 1.878 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$119,486 and the median annual saving was US$98,952. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for installing equipment to utilize waste fuel. Lower quartile 0.429, median 1.89 and upper quartile 3.71 years.
Estimated payback for installing equipment to utilize waste fuel. Lower quartile 0.429, median 1.89 and upper quartile 3.71 years. Figure by Industry Applied.

What the records can support

The source lists 68 recommendations under assessment code 2.1336. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 68 comparable records, 18 carry the implemented flag and 47 the non-implemented flag. The remaining 3 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 2000–2014, 38 qualifying records had a median of 1.226 years. For fiscal years 2015–2026, 30 qualifying records had a median of 2.393 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

SD045201

2012

2000

48619

0.04113618

AM051504

2006

13000

29840

0.4356568

TT006003

2011

98000

51500

1.902913

WV038601

2008

517666

140425

3.686423

DL009906

2012

3600000

320000

11.25

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.503 years. At full forecast savings and a 20% higher installed cost, it would give 2.253 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.