The middle half of the estimated payback periods ran from 0.66667 to 2.3298 years for installing de-aerator in place of condensate tank, a spread of 1.6631 years. The median among 17 qualifying US proposals was 1.2157 years. Each proposal has equal weight.

The scope of the plant change

Log steam demand against finished output and record condensate return conditions. Distinguish planned start-up heating from continuous duty and align the baseline with boiler loading. A process change may shift costs between fuel, make-up water and treatment.

A recommendation you can reproduce

Recommendation IA001101 in US fiscal year 1991 pairs US$70,000 of implementation cost with US$57,580 in estimated annual net savings. Dividing the first figure by the second gives 1.216 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$30,000 and the median annual saving was US$19,946. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for installing de-aerator in place of condensate tank. Lower quartile 0.6667, median 1.216 and upper quartile 2.33 years.
Estimated payback for installing de-aerator in place of condensate tank. Lower quartile 0.6667, median 1.216 and upper quartile 2.33 years. Figure by Industry Applied.

What the records can support

The source lists 17 recommendations under assessment code 2.2124. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 17 comparable records, 7 carry the implemented flag and 9 the non-implemented flag. The remaining 1 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 4 qualifying records had a median of 2.481 years. For fiscal years 2000–2014, 10 qualifying records had a median of 0.7424 years. For fiscal years 2015–2026, 3 qualifying records had a median of 1.022 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

IC010504

2005

900

12910

0.0697134

NC051003

2014

1000

1500

0.6666667

IA001101

1991

70000

57580

1.2157

IC008004

2004

95360

40931

2.329774

UW240907

2024

223625

24670

9.064653

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.621 years. At full forecast savings and a 20% higher installed cost, it would give 1.459 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

What a two-year screening rule would have selected

Among the 17 proposals with a positive implementation cost, 11 (64.706%) had a forecast simple payback of two years or less. The calculation excludes 0 zero-cost records. For a local project with a two-year screening period, divide the quoted installed cost by two to find the minimum annual net saving needed. Use local currency and include the recurring cost of making the change.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.