Across 15 qualifying US industrial recommendations, the median projected simple payback was 5.558 years. The middle half ran from 4.232 to 6.896 years. Those figures describe the assessed proposals for installing anaerobic digester, in fiscal years 2008 to 2026.

The scope of the plant change

Define the work package in physical terms and identify which meter, production counter or invoice can capture its effect. Record a representative operating cycle before changing the process and retain the underlying unit prices alongside measured quantities.

A recommendation you can reproduce

Recommendation IC031812 in US fiscal year 2025 pairs US$9,930,710 of implementation cost with US$1,786,748 in estimated annual net savings. Dividing the first figure by the second gives 5.558 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$3,468,069 and the median annual saving was US$544,130. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

What the records can support

The source lists 15 recommendations under assessment code 2.9141. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 15 comparable records, 5 carry the implemented flag and 9 the non-implemented flag. The remaining 1 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 2000–2014, 4 qualifying records had a median of 3.213 years. For fiscal years 2015–2026, 11 qualifying records had a median of 5.754 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

OK076605

2008

240000

304567

0.788004

UF065201

2026

200000

43759

4.570488

IC031812

2025

9930710

1786748

5.55798

SF056605

2021

1222260

189018

6.466368

UU021701

2023

7400000

648030

11.41922

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 7.411 years. At full forecast savings and a 20% higher installed cost, it would give 6.67 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.