Across 175 qualifying US industrial recommendations, the median projected simple payback was 0.1984 years. The middle half ran from 0.0805 to 0.7021 years. Those figures describe the assessed proposals for industrial water leak repair, in fiscal years 1983 to 2026.

The scope of the plant change

Build a night-flow baseline, allowing for cleaning or genuine continuous users. Isolate branches through the normal operating procedure and record water pressure and meter resolution. Compare water, pumping and discharge charges at their respective boundaries.

A recommendation you can reproduce

Recommendation CO024901 in US fiscal year 1992 pairs US$125 of implementation cost with US$630 in estimated annual net savings. Dividing the first figure by the second gives 0.1984 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$300 and the median annual saving was US$1,861. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for industrial water leak repair. Lower quartile 0.0805, median 0.1984 and upper quartile 0.7021 years.
Estimated payback for industrial water leak repair. Lower quartile 0.0805, median 0.1984 and upper quartile 0.7021 years. Figure by Industry Applied.

What the records can support

The source lists 197 recommendations under assessment code 3.4154. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 175 comparable records, 129 carry the implemented flag and 36 the non-implemented flag. The remaining 10 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

KS232108

2023

30

29979

0.0010007

TT031303

2024

340

4207.45

0.08080904

CO024901

1992

125

630

0.1984127

SF013111

1998

6000

8688

0.6906077

IC008407

2004

430000

2024

212.4506

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.2646 years. At full forecast savings and a 20% higher installed cost, it would give 0.2381 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.