Across 326 qualifying US industrial recommendations, the median projected simple payback was 2.846 years. The middle half ran from 1.476 to 4.82 years. Those figures describe the assessed proposals for industrial boiler replacement, in fiscal years 1982 to 2026.

The scope of the plant change

Start with the load-duration curve and the limiting steam or hot-water duty. Include commissioning, controls and downtime in installed cost. Compare part-load fuel consumption across typical production weeks as well as design efficiency.

A recommendation you can reproduce

Recommendation CM100506 in US fiscal year 2022 pairs US$4,800 of implementation cost with US$1,680 in estimated annual net savings. Dividing the first figure by the second gives 2.857 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$42,120 and the median annual saving was US$17,342. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for industrial boiler replacement. Lower quartile 1.476, median 2.846 and upper quartile 4.82 years.
Estimated payback for industrial boiler replacement. Lower quartile 1.476, median 2.846 and upper quartile 4.82 years. Figure by Industry Applied.

What the records can support

The source lists 333 recommendations under assessment code 2.1224. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 326 comparable records, 102 carry the implemented flag and 192 the non-implemented flag. The remaining 32 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

LE039402

2015

75

16261

0.004612262

SF033204

2006

1003522

683163

1.468935

OK061510

2001

22000

7761

2.834686

CI002808

2024

8000

1659

4.822182

OK109802

2023

78000

2974

26.2273

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 3.81 years. At full forecast savings and a 20% higher installed cost, it would give 3.429 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.