Across 7 qualifying US industrial recommendations, the median projected simple payback was 1.378 years. The middle half ran from 0.9455 to 2.003 years. Those figures describe the assessed proposals for increasing electrical conductor size to reduce distribution losses, in fiscal years 1993 to 2017.

The scope of the plant change

Read interval demand and production together. Identify whether the changed quantity is energy, peak demand or a fixed charge before assigning a tariff. Use the same billing boundary across the comparison and allow for coincident loads outside the project.

A recommendation you can reproduce

Recommendation NV010802 in US fiscal year 1998 pairs US$15,808 of implementation cost with US$11,472 in estimated annual net savings. Dividing the first figure by the second gives 1.378 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$15,808 and the median annual saving was US$11,472. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for increasing electrical conductor size to reduce distribution losses. Lower quartile 0.9455, median 1.378 and upper quartile 2.003 years.
Estimated payback for increasing electrical conductor size to reduce distribution losses. Lower quartile 0.9455, median 1.378 and upper quartile 2.003 years. Figure by Industry Applied.

What the records can support

The source lists 7 recommendations under assessment code 2.3522. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 7 comparable records, 4 carry the implemented flag and 3 the non-implemented flag. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

2 of 7 comparable proposals had an estimated payback of one year or less. 7 carried a positive implementation cost. Inspect zero-cost and positive-cost proposals separately when comparing a change in operating practice with a capital project.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

ME013208

1994

1200

4892

0.2452984

TT001404

2007

51000

44581

1.143985

NV010802

1998

15808

11472

1.377964

LE043705

2017

50000

35693

1.400835

NC025101

2002

130000

29079

4.47058

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.837 years. At full forecast savings and a 20% higher installed cost, it would give 1.654 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.