Across 336 qualifying US industrial recommendations, the median projected simple payback was 0.8926 years. The middle half ran from 0.3776 to 1.646 years. Those figures describe the assessed proposals for increasing amount of condensate returned, in fiscal years 1983 to 2026.

The scope of the plant change

Log steam demand against finished output and record condensate return conditions. Distinguish planned start-up heating from continuous duty and align the baseline with boiler loading. A process change may shift costs between fuel, make-up water and treatment.

A recommendation you can reproduce

Recommendation DL014401 in US fiscal year 2015 pairs US$100,000 of implementation cost with US$112,390 in estimated annual net savings. Dividing the first figure by the second gives 0.8898 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$8,000 and the median annual saving was US$12,562. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for increasing amount of condensate returned. Lower quartile 0.3776, median 0.8926 and upper quartile 1.646 years.
Estimated payback for increasing amount of condensate returned. Lower quartile 0.3776, median 0.8926 and upper quartile 1.646 years. Figure by Industry Applied.

What the records can support

The source lists 354 recommendations under assessment code 2.2121. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 336 comparable records, 160 carry the implemented flag and 167 the non-implemented flag. The remaining 9 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 126 qualifying records had a median of 0.813 years. For fiscal years 2000–2014, 145 qualifying records had a median of 0.9504 years. For fiscal years 2015–2026, 65 qualifying records had a median of 1.085 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

OR050101

2006

200

119000

0.001680672

WV022401

2001

13233

34989

0.3782046

NC032501

2005

25000

27917

0.8955117

LL015703

2003

6875

4189

1.641203

IC026601

2022

58751

5894

9.967933

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.186 years. At full forecast savings and a 20% higher installed cost, it would give 1.068 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.