Across 1,920 qualifying US industrial recommendations, the median projected simple payback was 1.574 years. The middle half ran from 0.8041 to 2.586 years. Those figures describe the assessed proposals for flue-gas heat recovery for preheating, in fiscal years 1982 to 2026.
The scope of the plant change
Map exhaust temperature against the receiving stream during actual production. Budget for fouling, bypass operation and cleaning access. Annual recovered heat should use only hours in which both streams are available.
A recommendation you can reproduce
Recommendation MA055403 in US fiscal year 2004 pairs US$76,341 of implementation cost with US$48,636 in estimated annual net savings. Dividing the first figure by the second gives 1.57 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.
The median implementation cost was US$13,000 and the median annual saving was US$9,306. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

What the records can support
The source lists 1,940 recommendations under assessment code 2.2414. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.
Of the 1,920 comparable records, 354 carry the implemented flag and 1,486 the non-implemented flag. The remaining 80 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.
Worked data
Recommendation ID | US fiscal year | Implementation cost (USD) | Estimated annual net saving (USD) | Recalculated payback (years) |
|---|---|---|---|---|
IC008202 | 2004 | 1533 | 212513 | 0.007213676 |
UM027703 | 2005 | 3000 | 3729 | 0.8045052 |
UM016309 | 2000 | 90000 | 56997 | 1.57903 |
SU047208 | 2018 | 15784 | 6103 | 2.586269 |
GT024201 | 1985 | 20000 | 780 | 25.64103 |
Using the evidence in an Australian project
For the worked record, delivering only three quarters of its estimated annual saving would give 2.093 years. At full forecast savings and a 20% higher installed cost, it would give 1.884 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.
Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.
Sources and calculation files
The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.