Across 444 qualifying US industrial recommendations, the median projected simple payback was 1.824 years. The middle half ran from 0.9219 to 3.52 years. Those figures describe the assessed proposals for factory building-envelope insulation, in fiscal years 1993 to 2026.

The scope of the plant change

Survey distinct surface assemblies instead of applying the roof assumption to every elevation. Match the envelope area to conditioned operating hours. Compare weather-adjusted HVAC input around the change and record any simultaneous expansion.

A recommendation you can reproduce

Recommendation UF029407 in US fiscal year 2002 pairs US$18,574 of implementation cost with US$10,139 in estimated annual net savings. Dividing the first figure by the second gives 1.832 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$6,836 and the median annual saving was US$4,200. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for factory building-envelope insulation. Lower quartile 0.9219, median 1.824 and upper quartile 3.52 years.
Estimated payback for factory building-envelope insulation. Lower quartile 0.9219, median 1.824 and upper quartile 3.52 years. Figure by Industry Applied.

What the records can support

The source lists 449 recommendations under assessment code 2.7491. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 444 comparable records, 110 carry the implemented flag and 282 the non-implemented flag. The remaining 52 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

MUCM3008

2025

27

647.12

0.04172333

BD008801

1997

18325

19848

0.9232668

UF029407

2002

18574

10139

1.831936

UF020304

1998

4200

1194

3.517588

OR078805

2024

200000

3766

53.10674

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.443 years. At full forecast savings and a 20% higher installed cost, it would give 2.198 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.