Across 33 qualifying US industrial recommendations, the median projected simple payback was 0.509 years. The middle half ran from 0.2133 to 1.259 years. Those figures describe the assessed proposals for doing not use compressed air for personal cooling, in fiscal years 1995 to 2024.
The scope of the plant change
Use a compressor input-power trace and a demand-side pressure trace from the same clock. Identify periods when the production line is idle, then check which air uses continue. A changed setpoint or a different compressor sequence changes the baseline.
A recommendation you can reproduce
Recommendation UF024807 in US fiscal year 2000 pairs US$909 of implementation cost with US$1,786 in estimated annual net savings. Dividing the first figure by the second gives 0.509 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.
The median implementation cost was US$1,212 and the median annual saving was US$1,914. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

What the records can support
The source lists 47 recommendations under assessment code 2.4238. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.
Of the 33 comparable records, 16 carry the implemented flag and 16 the non-implemented flag. The remaining 1 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.
How the assessment mix affects the comparison
For fiscal years 1980–1999, 5 qualifying records had a median of 0.7917 years. For fiscal years 2000–2014, 17 qualifying records had a median of 0.509 years. For fiscal years 2015–2026, 11 qualifying records had a median of 0.4974 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.
Worked data
Recommendation ID | US fiscal year | Implementation cost (USD) | Estimated annual net saving (USD) | Recalculated payback (years) |
|---|---|---|---|---|
IP009002 | 2017 | 110 | 3956 | 0.02780586 |
MI041203 | 2022 | 2055 | 9634 | 0.213307 |
UF024807 | 2000 | 909 | 1786 | 0.5089586 |
WV029228 | 2004 | 2088 | 1659 | 1.25859 |
UF026501 | 2000 | 1196 | 367 | 3.258856 |
Using the evidence in an Australian project
For the worked record, delivering only three quarters of its estimated annual saving would give 0.6786 years. At full forecast savings and a 20% higher installed cost, it would give 0.6108 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.
Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.
Sources and calculation files
The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.