Across 321 qualifying US industrial recommendations, the median projected simple payback was 0.4792 years. The middle half ran from 0.1406 to 1.193 years. Those figures describe the assessed proposals for disconnecting ballasts, in fiscal years 1984 to 2026.

The scope of the plant change

Record the circuit load, lighting hours and the actual visual task in the work area. Use separately controlled zones as measurement boundaries. Keep a record of daylight, shift occupancy and any maintenance intervention between the baseline and follow-up periods.

A recommendation you can reproduce

Recommendation MS008702 in US fiscal year 1997 pairs US$150 of implementation cost with US$313 in estimated annual net savings. Dividing the first figure by the second gives 0.4792 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$345 and the median annual saving was US$980. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for disconnecting ballasts. Lower quartile 0.1406, median 0.4792 and upper quartile 1.193 years.
Estimated payback for disconnecting ballasts. Lower quartile 0.1406, median 0.4792 and upper quartile 1.193 years. Figure by Industry Applied.

What the records can support

The source lists 428 recommendations under assessment code 2.7122. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 321 comparable records, 164 carry the implemented flag and 146 the non-implemented flag. The remaining 11 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 110 qualifying records had a median of 0.899 years. For fiscal years 2000–2014, 178 qualifying records had a median of 0.3288 years. For fiscal years 2015–2026, 33 qualifying records had a median of 0.3704 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

UF026405

2000

22

4531

0.00485544

UD067415

2003

44

313

0.1405751

MS008702

1997

150

313

0.4792332

MS019706

2001

340

285

1.192982

OK056701

1999

429

49

8.755102

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.639 years. At full forecast savings and a 20% higher installed cost, it would give 0.5751 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.