Across 1,191 qualifying US industrial recommendations, the median projected simple payback was 0.6429 years. The middle half ran from 0.2691 to 1.419 years. Those figures describe the assessed proposals for daylight-responsive lighting controls, in fiscal years 1991 to 2026.

The scope of the plant change

Record daylight and lighting circuit demand at the same times. Compare perimeter and interior workstations at the required illuminance. A photocell serving the whole building can leave the interior controlling the switching decision.

A recommendation you can reproduce

Recommendation AM081807 in US fiscal year 2020 pairs US$450 of implementation cost with US$700 in estimated annual net savings. Dividing the first figure by the second gives 0.6429 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$600 and the median annual saving was US$1,100. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for daylight-responsive lighting controls. Lower quartile 0.2691, median 0.6429 and upper quartile 1.419 years.
Estimated payback for daylight-responsive lighting controls. Lower quartile 0.2691, median 0.6429 and upper quartile 1.419 years. Figure by Industry Applied.

What the records can support

The source lists 1,234 recommendations under assessment code 2.7134. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 1,191 comparable records, 461 carry the implemented flag and 668 the non-implemented flag. The remaining 62 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

BD028306

2005

5

1499

0.003335557

OK058903

2000

136

504

0.2698413

AM081807

2020

450

700

0.6428571

SD052006

2015

2590

1826

1.418401

CO061903

2009

20000

1710

11.69591

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.8571 years. At full forecast savings and a 20% higher installed cost, it would give 0.7714 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Reconcile the proposed baseline and the acceptance test in the same spreadsheet. Record the meter boundary, operating hours and product output in both periods. Keep any downtime allowance separate from recurring savings when comparing two options.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.