Across 6 qualifying US industrial recommendations, the median projected simple payback was 1.258 years. The middle half ran from 0.5688 to 3.208 years. Those figures describe the assessed proposals for converting to robotic painting, in fiscal years 1995 to 2025.

The scope of the plant change

Define the work package in physical terms and identify which meter, production counter or invoice can capture its effect. Record a representative operating cycle before changing the process and retain the underlying unit prices alongside measured quantities.

A recommendation you can reproduce

Recommendation LE059803 in US fiscal year 2025 pairs US$362,095 of implementation cost with US$218,856 in estimated annual net savings. Dividing the first figure by the second gives 1.654 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$132,000 and the median annual saving was US$98,280. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for converting to robotic painting. Lower quartile 0.5688, median 1.258 and upper quartile 3.208 years.
Estimated payback for converting to robotic painting. Lower quartile 0.5688, median 1.258 and upper quartile 3.208 years. Figure by Industry Applied.

What the records can support

The source lists 6 recommendations under assessment code 3.2173. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 6 comparable records, 1 carry the implemented flag and 3 the non-implemented flag. The remaining 2 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

3 of 6 comparable proposals had an estimated payback of one year or less. 6 carried a positive implementation cost. Inspect zero-cost and positive-cost proposals separately when comparing a change in operating practice with a capital project.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

CW012104

2022

33000

93600

0.3525641

CW012203

2022

48500

102960

0.4710567

UD046502

1995

200000

232030

0.8619575

LS221810

2022

140000

37576

3.725782

UF034605

2004

124000

24976

4.964766

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.206 years. At full forecast savings and a 20% higher installed cost, it would give 1.985 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.