Across 30 qualifying US industrial recommendations, the median projected simple payback was 0.8473 years. The middle half ran from 0.3515 to 1.25 years. Those figures describe the assessed proposals for converting to aqueous cleaning system, in fiscal years 1994 to 2015.

The scope of the plant change

Define the work package in physical terms and identify which meter, production counter or invoice can capture its effect. Record a representative operating cycle before changing the process and retain the underlying unit prices alongside measured quantities.

A recommendation you can reproduce

Recommendation AM033407 in US fiscal year 1998 pairs US$1,030 of implementation cost with US$1,260 in estimated annual net savings. Dividing the first figure by the second gives 0.8175 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$1,300 and the median annual saving was US$1,791. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for converting to aqueous cleaning system. Lower quartile 0.3515, median 0.8473 and upper quartile 1.25 years.
Estimated payback for converting to aqueous cleaning system. Lower quartile 0.3515, median 0.8473 and upper quartile 1.25 years. Figure by Industry Applied.

What the records can support

The source lists 34 recommendations under assessment code 3.8211. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 30 comparable records, 16 carry the implemented flag and 13 the non-implemented flag. The remaining 1 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

20 of 30 comparable proposals had an estimated payback of one year or less. 30 carried a positive implementation cost. Inspect zero-cost and positive-cost proposals separately when comparing a change in operating practice with a capital project.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

IA025807

2000

420

56437

0.007441926

SD021809

1999

1000

2926

0.3417635

AM033407

1998

1030

1260

0.8174603

OD011104

1998

1300

1029

1.263362

AM024508

1995

3600

1060

3.396226

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 1.09 years. At full forecast savings and a 20% higher installed cost, it would give 0.981 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.