Across 16 qualifying US industrial recommendations, the median projected simple payback was 0.7331 years. The middle half ran from 0.2905 to 1.345 years. Those figures describe the assessed proposals for converting combustion equipment to burn oil, in fiscal years 1986 to 2012.

The scope of the plant change

Map the heated product, the hot exhaust and the periods when the process keeps equipment warm between batches. Express fuel use per accepted unit alongside total fuel. A change in product mix or loading can move those measures in opposite directions.

A recommendation you can reproduce

Recommendation CO048503 in US fiscal year 2001 pairs US$30,000 of implementation cost with US$40,450 in estimated annual net savings. Dividing the first figure by the second gives 0.7417 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$12,200 and the median annual saving was US$21,622. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for converting combustion equipment to burn oil. Lower quartile 0.2905, median 0.7331 and upper quartile 1.345 years.
Estimated payback for converting combustion equipment to burn oil. Lower quartile 0.2905, median 0.7331 and upper quartile 1.345 years. Figure by Industry Applied.

What the records can support

The source lists 19 recommendations under assessment code 2.1333. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 16 comparable records, 4 carry the implemented flag and 11 the non-implemented flag. The remaining 1 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 8 qualifying records had a median of 0.3987 years. For fiscal years 2000–2014, 8 qualifying records had a median of 0.9174 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

GT030006

1986

2000

149681

0.01336175

GT028608

1986

5000

16626

0.3007338

CO048503

2001

30000

40450

0.7416564

IC014612

2008

32868

27915

1.177431

IC013911

2008

23865

7860

3.03626

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 0.9889 years. At full forecast savings and a 20% higher installed cost, it would give 0.89 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.