Across 569 qualifying US industrial recommendations, the median projected simple payback was 1.567 years. The middle half ran from 0.9889 to 2.354 years. Those figures describe the assessed proposals for conserving energy by efficient use of vending machines, in fiscal years 1986 to 2026.

The scope of the plant change

Define the work package in physical terms and identify which meter, production counter or invoice can capture its effect. Record a representative operating cycle before changing the process and retain the underlying unit prices alongside measured quantities.

A recommendation you can reproduce

Recommendation SU028010 in US fiscal year 2009 pairs US$1,009 of implementation cost with US$644 in estimated annual net savings. Dividing the first figure by the second gives 1.567 years. This record was selected by proximity to the median payback, with the more recent assessment preferred when ratios tie.

The median implementation cost was US$516 and the median annual saving was US$327. Those two medians can come from different facilities. To obtain the payback distribution, divide cost by annual savings within each recommendation and take percentiles of the resulting years. Zero-cost measures remain in the calculation. The table selects actual records at five ordered positions, so its rounded examples can differ slightly from interpolated percentiles.

Estimated payback for conserving energy by efficient use of vending machines. Lower quartile 0.9889, median 1.567 and upper quartile 2.354 years.
Estimated payback for conserving energy by efficient use of vending machines. Lower quartile 0.9889, median 1.567 and upper quartile 2.354 years. Figure by Industry Applied.

What the records can support

The source lists 647 recommendations under assessment code 2.6211. The analysis retains records with a reported fiscal year, a non-negative implementation cost and positive net annual monetary savings. It sums the reported primary, secondary, tertiary and quaternary dollar savings, preserving recorded costs or offsets. A missing savings field contributes nothing only when at least one resource has a recorded value.

Of the 569 comparable records, 107 carry the implemented flag and 418 the non-implemented flag. The remaining 44 have another or unreported status. These are administrative outcomes. They do not establish the saving subsequently measured at an individual plant.

How the assessment mix affects the comparison

For fiscal years 1980–1999, 23 qualifying records had a median of 1.254 years. For fiscal years 2000–2014, 274 qualifying records had a median of 1.576 years. For fiscal years 2015–2026, 272 qualifying records had a median of 1.633 years. Grouping by year changes the mix of facilities and proposals. The medians are descriptive, and the database does not establish a causal trend over time.

Worked data

Recommendation ID

US fiscal year

Implementation cost (USD)

Estimated annual net saving (USD)

Recalculated payback (years)

IC013111

2007

1

864

0.001157407

CL200704

2020

630

637.06

0.9889178

SU028010

2009

1009

644

1.56677

SU050308

2021

186

79

2.35443

ORC01604

2025

7000

838

8.353222

Using the evidence in an Australian project

For the worked record, delivering only three quarters of its estimated annual saving would give 2.089 years. At full forecast savings and a 20% higher installed cost, it would give 1.88 years. These are sensitivity calculations using the same original proposal. A local business case needs quotations and a current Australian tariff or material price.

Run the local comparison over the same production duty in both cases. Keep a separate column for incentives, scheduled replacement and avoided maintenance so that the engineering change can be evaluated at both full and incremental cost.

Sources and calculation files

The assessment-code results and the US Industrial Training and Assessment Centers database download contain the original recommendations. Dollar amounts are nominal US dollars for the assessment year. The Australian Government equipment guides provide local context. Download the worked records as CSV.